施工场地挖运土方工程量
序号 计 算 式(单位: m3)
1-1 [(93.149+92.991+93.589+94.106) /4-90.2) ×100=325.88
1-2 [(92.991+92.543+94.106+93.196)/4-90.2] ×100=300.90
1-3 [(92.543+92.452+93.196+92.336)/4 -90.2] ×100=243.18
1-4 [(92.452+92.336)/2 -90.2] ×(6.2+9.38)/2 ×10=170.91
2-1 [(93.569+94.106+93.039+92.796)/4 -90.2] ×100=317.75
2-2 [(94.106+93.196+92.796+93.169)/4 -90.2] ×100=311.68
2-3 [(93.196+92.336+93.169+92.152