高压线防护施工措施
编制单位:
编制时间:
目 录
1. 编制依据 ·························· 3
2. 工程概况 ·························· 3
2.1. 施工现场与周围环境 ···················· 3
3. 施工安排 ·························· 5
3.1. 工期安排 ························· 5
3.2. 施工组织及任务划分 ···················· 5
3.3. 高压线防护脚手架形式选择 ················· 5
4. 施工准备 ·························· 6
4.1. 材料准备 ························· 6
4.2. 技术准备 ················